We have signed a 8.8MW solar plant construction contract of a whole 20MW capacity that was on progress with \"SO company\".
<?xml:namespace prefix = o ns = \"urn:schemas-microsoft-com:office:office\" />
This project costs about 2,200 million won for the total construction and is scheduled for setting-up this July, pre-operation inspection this October, will be completed by the end of this year.Every PV module to be used for this project is a TOPSUN’s 400Wp model and 22,000 quantities are required .18 sets of a 500kW-inverter is to be used.
A 12-year-agreement with KEPCO makes it possible to sell the produced energy for 12 years.
As a part of 20MW solar plant plans, if it is completed successfully, the other 11.2MW project will also be made possible and increases our long-term sales revenue.
As an expert company of a solar industry we “TOPSUN” try the best to achieve sustainable growth.